For MOUs under construction or conversion, ref. Section 6 below, a surveyor approved by the claims leader shall be appointed to review the project plans and procedures for moves and lifts and, when applicable, offshore installation of components or modules, and prepare an initial risk assessment. On the basis of the initial risk assessment the claims leader shall approve the scope of survey levels required for the identified risk levels.
When required by the claims leader for certain operations as per the scope of survey, the surveyor shall issue a certificate of approval when he is satisfied with the preparations for the operation. The operation at issue can commence upon receipt of the surveyor’s signed certificate of approval.