Forsikringen omfatter krigsfare, jfr. § 2-9, med unntak for streik og lock out.
The range of perils insured under the builders’ risks insurance contract has been reduced as regards war perils, cf. Cl. 19-1. The main rule is that only marine perils are covered by the insurance. Cl. 19-1 refers to Cl. 2-8, which means that the distinction between marine perils and war perils...
Assurandørens ansvar begynner å løpe når forsikringsobjektet er sjøsatt.
For maskineri, deler og materialer begynner ansvaret likevel først å løpe når de er kommet ombord i det sjøsatte forsikringsobjektet.
Sub-clause 1 states that the insurance does not attach until the subject-matter insured has been launched. While the subject-matter insured is on land it thus has no war risk cover. The limitation has to do with the fact that it is not until after the subject-matter insured has been launched that...
Reglene i kapittel 19 avsnitt 1 til 4 får tilsvarende anvendelse på denne forsikring.
For forsikringen gjelder også § 15-5, § 15-6 og § 15-8.
Sub-clause 1 states that the provisions in Sections 1 to 4 shall apply to the war risks insurance. The war risks insurance thus partly covers hull insurance, partly damage and costs recoverable under Section 3, and partly liability insurance for the yard under Section 4. Sub-clause 2 refers to Cl...